Lessons Report

The Lessons Report is used to pass on any lessons that can be usefully applied to other projects. The purpose of the report is to provoke action so that the positive lessons become embedded in the organization’s way of working, and that the organization is able to avoid any negative lessons on future projects.

A Lessons Report can be created at any time in a project and should not necessarily wait to the end. Typically it should be included as part of the End Stage Report and End Project Report. It may be appropriate (and necessary) for there to be several Lessons Reports specific to the particular organization (e.g. user, supplier, corporate or programme).
The data in the report should be used by the corporate group that is responsible for the quality management system, in order to refine, change and improve the standards. Statistics on how much effort was needed for products can help improve future estimating.

PRINCE2® Lessons Report to download PDF

PRINCE2® Lessons Report to download WORD


The Lessons Report should cover the following topics.

  • Executive Summary    3
  • Overall Review    3
  • Review of Useful Measures    3
  • Significant Lessons    4

Derivation

The Lessons Report is derived from the following documents: Project Initiation Documentation (for the baseline position); Lessons Log (for identification of lessons); Quality Register, Issue Register and Risk Register (for statistical analysis); Quality records (for statistical analysis) and Communication Management Strategy (for the distribution list).


The Lessons Report can take a number of formats, including: Oral report to the Project Board (could be in person or over the phone); Presentation at a progress meeting (physical meeting or conference call); Document or email to the Project Board; Entry in a project management tool.

The following quality criteria should be observed:

  • Every management control has been examined
  • Statistics of estimates versus actuals are provided
  • Statistics of the success of quality controls used are included
  • Any appointed Project Assurance roles agree with the report
  • Unexpected risks are reviewed to determine whether they could have been anticipated
  • Recommended actions are provided for each lesson (note that lessons are not ‘learned’ until action is taken).

Creation, update and use

The Lessons Report is created by the Project Manager from the relevant records within the Lessons log. The Lessons Report contains the lessons learned, which could be useful for the future projects. The Lesson Report is created is typically created at the Closing a Project process, but the Project Manager can create it at any time during the project.

The Lessons Report will be used by other Project Managers, when they are looking for lesoons and experience relevant for their project.

 

Comments

Sign up to make a comment.

Quick information

PRINCE2 Practitioner for PMP, IPMA

Owner of PMP certificates and IPMA certificates can now pass PRINCE2 Practitioner without passing Foundation certification.


We are PRINCE2 Professionals

We reached the highest certificate PRINCE2 progfessional. Our practical experience from managing PRINCE2 projects is widely used by the commercial companies.


Do you want to be Agile?

We expanded the portfolio of our training by Agile methodologies, such as Agile Management by APMG and SCRUM by SCRUMstudy.

>>>

News

PRINCE2 in Russia

We successfully expanded to the Russian market with PRINCE2 certification. Trainings. was organized by the Voronezh Institute of High Technologies (VIHT) and will continue on the other organizations.

PRINCE2 Foundation training in Russia