Plan

A plan provides a statement of how and when objectives are to be achieved, by showing the major products, activities and resources required for the scope of the plan. In PRINCE2, there are three levels of plan: project, stage and team. Team Plans are optional and may not need to follow the same composition as a Project Plan or Stage Plan.

PRINCE2® Plan to download PDF

PRINCE2® Plan to download WORD

An Exception Plan is created at the same level as the plan that it is replacing.
A Project Plan provides the Business Case with planned costs, and it identifies the management stages and other major control points. It is used by the Project Board as a baseline against which to monitor project progress.

Stage Plans cover the products, resources, activities and controls specific to the stage and are used as a baseline against which to monitor stage progress.
Team Plans (if used) could comprise just a schedule appended to the Work Package(s) assigned to the Team Manager.

A plan should cover not just the activities to create products but also the activities to manage product creation - including activities for assurance, quality management, risk management, configuration management, communication and any other project controls required.


The Plan should cover the following topics. 

  • Plan Description    4
  • Plan Prerequisites    4
  • External Dependencies    4
  • Planning Assumptions    4
  • Lessons Incorporated    5
  • Monitoring and Control    5
  • Budgets    5
  • Tolerances    5
  • Product Descriptions    5
  • Schedule    6


The Plan is derived from the Project Brief, Quality Management Strategy (for quality management activities to be included in the plan), Risk Management Strategy (for risk management activities to be included in the plan), Communication Management Strategy (for communication management activities to be included in the plan), Configuration Management Strategy (for configuration management activities to be included in the plan), Resource availability, and Registers and logs.

The Plan can take a number of formats including: A stand-alone document or a section of the Project Initiation Documentation; Document, spreadsheet, presentation slides or mindmap; Entry in a project management tool.
The schedule may be in the form of a product checklist (which is a list of the products to be delivered within the scope of the plan, together with key status dates such as draft ready, quality inspected, approved etc.) or the output from a project planning tool.


The following quality criteria should be observed:

  • The plan is achievable
  • Estimates are based on consultation with the resources, who will undertake the work, and/or historical data
  • Team Managers agree that their part of the plan is achievable
  • It is planned to an appropriate level of detail (not too much, not too little)
  • The plan conforms to required corporate or programme standards
  • The plan incorporates lessons from previous projects
  • The plan incorporates any legal requirements
  • The Plan covers management and control activities (such as quality) as well as the activities to create the products in scope
  • The plan supports the Quality Management Strategy, Configuration Management Strategy, Risk Management Strategy, Communication Management Strategy and project approach
  • The plan supports the management controls defined in the Project Initiation Documentation

Creation, update and use

The Project Plan is created in the Initiating a Project  Process. The Project Manager prepares the Project and Stage Plans using the Product Based Planning Technique.

The Project Plan is updated in the Managing a Stage Boundary process and the Stage Plan is upadted in the Controlling a Stage process. The Team Plan is created and updated in the Managing a Product Delivery process. 

The Project Plan is used by the Project Board to verify that the project is develloping as planned. The Stage plan is used by the Project Manager to monitor the progress of the stage and the Team Plan is used by both the Project Manager and the Team Manger to check the development of the products.

Comments

Sign up to make a comment.

Quick information

PRINCE2 Practitioner for PMP, IPMA

Owner of PMP certificates and IPMA certificates can now pass PRINCE2 Practitioner without passing Foundation certification.


We are PRINCE2 Professionals

We reached the highest certificate PRINCE2 progfessional. Our practical experience from managing PRINCE2 projects is widely used by the commercial companies.


Do you want to be Agile?

We expanded the portfolio of our training by Agile methodologies, such as Agile Management by APMG and SCRUM by SCRUMstudy.

>>>

News

PRINCE2 in Russia

We successfully expanded to the Russian market with PRINCE2 certification. Trainings. was organized by the Voronezh Institute of High Technologies (VIHT) and will continue on the other organizations.

PRINCE2 Foundation training in Russia